Fayadieh:Roadworks in Fayadieh have reached their final phase after the Beirut and Mount Lebanon Water Establishment repaired a major water-line leak. Coordination with Electricit© du Liban was necessary due to buried high-voltage power lines within the work zone.
According to National news agency - Lebanon, these developments broadened the project's scope and delayed the original completion timeline. Public Works and Transport Minister Fayez Rasamny is monitoring the project's progress closely and has directed teams to expedite their efforts to meet the new completion date of Tuesday, October 6, 2026.
The Ministry of Public Works and Transport noted that with the water repairs and electricity inspections finalized, the remaining tasks include concrete injection, backfilling the excavation, and repaving the road.